Project Costs

Direct Cost Breakdown

Cost Item Amount
Materials -£61,797.46
Labourers -£21,720.00
Tradesmen -£36,400.00
Skip / Grab Hire -£4,340.00
Hire -£3,792.47
Other -£3,736.60
Total Expenses -£131,786.53
The above costs do not include company overheads.

Scope of Works

Brief Project Scope

Structural
  • Rear dormer
  • Full house refurbishment
  • Two en-suites + two main bathrooms
  • Front and rear garden paving and landscaping
MEP
  • Electrical
  • Plumbing & Heating
  • Data networking
Kitchens & Bathrooms
Supplied and installed by us.
Carpentry & Joinery
Supplied and installed by us.
Glazing
  • UPVC
Bathrooms & Tiling
Supplied by the client and installed by us.
Painting & Decorating
Painting according to client spec.